Step-by-Step Concrete Yardage Calculation
- 1. Surface Area: 12.00 ft × 20.00 ft × 1 slab = 240.00 sq ft.
- 2. Net Concrete Volume: 240.00 sq ft × (4.00 in ÷ 12 in/ft) = 80.00 cubic feet. Dividing by 27 ft³/yd³ gives 2.96 cubic yards net.
- 3. Waste-Adjusted Order Volume (+10%): 80.00 ft³ × 1.10 = 88.00 ft³ = 3.26 cubic yards (2.49 m³).
- 4. Pre-Mixed Bag Equivalents: 88.00 ft³ ÷ 0.60 ft³/bag = 147 bags (80 lb), or 196 bags (60 lb), or 294 bags (40 lb).
Detailed Slab Volume, Bag & Weight Breakdown
| Material / Engineering Metric | Net Theoretical Value (0% Waste) | Order Value (With Selected Waste) |
|---|---|---|
| Total Pour Surface Area | 240.00 sq ft | 240.00 sq ft |
| Volume in Cubic Yards (yd³) | 2.96 yd³ | 3.26 yd³ |
| Volume in Cubic Feet (ft³) | 80.00 ft³ | 88.00 ft³ |
| Volume in Cubic Meters (m³) | 2.27 m³ | 2.49 m³ |
| 80 lb Pre-Mix Bags (0.60 ft³ yield) | 134 bags | 147 bags |
| 60 lb Pre-Mix Bags (0.45 ft³ yield) | 178 bags | 196 bags |
| 40 lb Pre-Mix Bags (0.30 ft³ yield) | 267 bags | 294 bags |
| Estimated Concrete Weight (150 lbs/ft³) | 12,000 lbs (6.00 US tons) | 13,200 lbs (6.60 US tons) |
Concrete Slab & Yardage Formulas
Circular Slab Volume (ft³) = π × [Diameter (ft) ÷ 2]² × [Thickness (in) ÷ 12] × Qty
Cubic Yards (yd³) = Cubic Feet (ft³) ÷ 27
Order Volume with Waste = Net Volume × (1 + Waste % ÷ 100)
80 lb Bags = ⌈ft³ ÷ 0.60⌉ | 60 lb Bags = ⌈ft³ ÷ 0.45⌉ | 40 lb Bags = ⌈ft³ ÷ 0.30⌉
Standard Assumptions: Pre-mixed bag yields follow standard commercial concrete yields (1 cubic yard = 27 ft³ = forty-five 80 lb bags, sixty 60 lb bags, or ninety 40 lb bags). Normal-weight Portland cement concrete is calculated at 150 lbs per cubic foot (4,050 lbs per cubic yard).
Illustrative Concrete Slab Example
Example — 12 ft × 20 ft Single-Car Driveway at 4 Inches Thick (Illustrative):
- Step 1 (Area & Depth in Feet): 12 ft × 20 ft = 240 sq ft. Convert 4 inches to feet: 4 ÷ 12 = 0.3333 ft.
- Step 2 (Net Cubic Feet & Yards): 240 sq ft × 0.3333 ft = 80.00 ft³. Divide by 27 ft³/yd³ = 2.96 yd³ net.
- Step 3 (Add 10% Waste Allowance): 2.963 yd³ × 1.10 = 3.26 yd³ (88.00 ft³), or 147 bags of 80 lb concrete mix.
How to Use the Concrete Slab & Yardage Calculator
- Select Slab Geometry: Choose Rectangular Slab / Patio (Length × Width) or Circular Slab / Round Pad (Outer Diameter), or click a preset chip for standard patio, driveway, or garage dimensions.
- Enter Dimensions & Units: Enter your measurements and select the matching unit (
ft,in,yd,m, orcm) for each field. - Set Waste Buffer & Local Unit Prices: Keep the recommended 10% contractor buffer to account for subgrade variations, and optionally adjust local ready-mix ($/yd³) and 80 lb bag prices.
- Copy or Print Your Estimate: Review the cubic yardage, bag counts, and weight table, then click Copy Result or Print / Save PDF for your supplier order.
Frequently Asked Questions
One cubic yard equals 27 cubic feet. Because an 80 lb bag yields 0.60 ft³, it takes 45 bags of 80 lb concrete (27 ÷ 0.60) to make 1 cubic yard. A 60 lb bag yields 0.45 ft³, requiring 60 bags of 60 lb concrete per cubic yard, and a 40 lb bag (0.30 ft³) requires 90 bags per cubic yard.
Even a 0.5-inch dip in the compacted gravel subbase across a 4-inch slab increases actual concrete volume by 12.5%. Adding a 10% buffer prevents running short mid-pour and avoiding costly short-load delivery fees for a second truck.
For pours exceeding 1.5 to 2 cubic yards (68 to 90 bags of 80 lb concrete), ready-mix delivery is typically more cost-effective and saves hours of manual mixing while ensuring a uniform, monolithic pour.
Standard residential sidewalks, patios, and passenger-car driveways are typically poured at 4 inches thick. Garage floors, RV pads, and heavy pickup driveways are commonly poured at 5 to 6 inches thick.